Embodied Carbon, Insulation Comparison & Preliminary Envelope Loads

Embodied carbon of material options from user-entered EPD factors; insulation R-value comparison from user-entered R per inch; steady-state conductive heat loss Q = U A dT per surface. Not a carbon database, not an energy-code compliance check and not an equipment sizing load.

Method

energy-carbon 1.1

Engine

1.1.0

Output status

Preliminary - review required

Review

Awaiting review

Formulas

  • kg CO2e = quantity (EPD declared unit) x GWP (kg CO2e per declared unit, from the EPD); option total = sum of its lines
  • R = R per unit thickness x thickness; with the rest of the assembly, R total = R rest + R insulation (layers in series)
  • Thickness for a target R = target R / R per unit thickness
  • Q = U x A x (indoor - outdoor design temperature); 1 Btu/h = 0.29307107 W

Conventions

  • Quantities are entered in each EPD’s own declared unit.
  • U-factors come from the Envelope calculator or are entered with a source.
  • Every factor carries the source the user gave.

Limits - what it will not do

  • No EPD, GWP factor, R-value or design temperature is built in.
  • EPD comparability (product category rules, functional unit, stages) is not checked; a warning shows when the stages differ.
  • Conduction only: no air leakage, ventilation, solar or internal gains. Not a heating load for sizing equipment and not an energy-code compliance check (use DOE COMcheck or REScheck).

Who must review it

  • Sustainability consultant or LCA practitioner: EPD comparability for the options compared
  • Mechanical engineer: design conditions and any use of the conductive loss

Worked example

Inputs Option A 1,200 m² x 2.5 + 40 m³ x 300; Option B 1,200 m² x 1.8 + 40 m³ x 250; R 5.0/in x 3 in and R 3.7/in x 4 in, target R-20; walls 1,000 ft² U 0.05 and roof 2,000 ft² U 0.032 at 70 to 0 degF

Expected A 15,000, B 12,160 kg CO2e (A +2,840, +23.4%); R-15 and R-14.8, 4 in and 5.41 in for R-20; 3,500 + 4,480 = 7,980 Btu/h

Checked by an automated test on every change.

Sources