Peer review and constructability
What a peer review is and who may do it, how constructability is defined, the edge-metal tests, joint intervals and metal movement a reviewer checks a flashing detail against, and a worked review of a constructed parapet run with its defects and fixes.
4 lessons · about 42 min · 11 diagrams · 0 videos
Version 1.0.0
Builds on these modules
Lessons
0 of 4 complete
Lesson 1 · 11 min · 12 slides · 8 questions
Peer review and constructability: principles and terminology
What a peer review is under NIBS Guideline 3, what makes it independent, how CII defines constructability, and the ladder of checks a flashing detail passes before AFS fabricates it: designer, contractor QC, approval, AFS shop confirmation.
You will be able to: Define peer review, independent peer review and constructability with their sources, name each step of the review ladder on a flashing job, and state what review does not do.
Not startedStart →Lesson 2 · 11 min · 12 slides · 8 questions
Peer review and constructability: materials, standards and design constraints
Edge-metal tests RE-1 to RE-3 and the building code, expansion-joint intervals in a federal guide spec, thermal movement by metal from the AFS register, dissimilar metals, and where AFS's piece length, flat width and bend limits sit against all of them.
You will be able to: Name what a reviewer measures a flashing detail against: the edge-metal tests in the building code, joint intervals in a federal guide spec, each metal's expansion, dissimilar-metal contact, and AFS's fabrication limits, with the source of each value.
Not startedStart →Lesson 3 · 10 min · 12 slides · 6 questions
Peer review and constructability: methods and worked application
A six-step review method, then a constructed 62.5 ft parapet run worked through it: how many pieces, where the joints go and how far each span moves, why one cap is too wide, and why the narrower 40 in cap still fails in 16 ga.
You will be able to: Apply a six-step documented review method to a constructed parapet coping run, recording the documents, assumptions, units and evidence for four findings: piece count, joints and movement, flat width and thickness.
Not startedStart →Lesson 4 · 10 min · 12 slides · 6 questions
Peer review and constructability: defects, verification and case study
The defect families a review finds, why attachments to tested edge metal matter, the verification steps of mock-up, preparatory, initial and follow-up phases, and a constructed case where a lightning conductor is clamped through a coping cap.
You will be able to: Diagnose a plausible edge-metal defect, name the defect families a review looks for, work through the verification steps from mock-up to follow-up inspection, and document the finding with evidence and corrective options.
Not startedStart →
Practical task
Review one coping or edge-flashing detail of your own choosing (or the constructed parapet run from lesson 3) as a second reviewer would: collect and date the documents, mark the interfaces, check each number against its source, log the findings with evidence, and write how each is closed.
Hand in
- A decision rationale: the documents the detail depends on, each with its edition or date, and who reviews what and at which stage
- A marked-up sketch of the section showing flat width, hem return, end flange, cleat and fastener, joint location and isolation points
- An assumptions sheet with units: material, thickness, run length, piece length, splice lap, temperature swing, each labelled as from a document, from AFS limits or assumed
- A finding log with location, reason, evidence, severity and owner for at least four findings, including one number check against AFS limits and one joint-and-movement calculation
- A defect analysis for one edge-metal finding: what failed, the evidence, the corrective options and how the fix goes back up the review ladder
Rubric
| Criterion | Meets the standard when |
|---|---|
| Sources | Every number names the document or AFS limit it comes from, and any federal guide-spec value is labelled as a guide-spec value, not code. |
| Method | The review follows the six steps in order and nothing is judged by look alone. |
| Calculations | Piece count and movement are worked with the inputs, units and assumptions shown, and rounded the way the lessons round them. |
| Findings | Each finding has a location, a reason, evidence, a severity and an owner, and none is closed without a dated fix. |
| Boundaries | The packet leaves wind and structural sign-off to the engineer of record and gives no instruction for working at heights. |