Windows, doors and opening transitions · Lesson 3 of 4

Windows, doors and opening transitions: methods and worked application

The installation sequence from pan flashing to head flashing, which sealant and tape rules belong to which product, metal pan and storefront details, and four worked examples with every input labelled.

You will be able to: Follow the crew sequence for a flanged window with the WRB on, apply the lap and sealant rules, and work out head piece, jamb flashing and sill pan lengths from labelled example inputs while recording assumptions and units.

15 min · 12 slides · 10 questions

All lessons in this module
Slide 1 of 12

The crew sequence

The TechNote's sequence for a flanged window with the WRB on. Read the maker's instructions first; DuPont wants the rough sill level or sloped out.

  • Prepare the WRB: cut, fold in at jambs, fold up at head
  • Install the pan flashing
  • Set the window to the maker's instructions
  • Install the jamb flashing
  • Install the head flashing (TN05 step 5)
  • Fold the flap down and tape the diagonals
Crew sequence for a flanged window with the WRB already onA top-to-bottom flow: read the maker's instructions, then the TechNote's six numbered steps in order: prepare the WRB, install the pan flashing, install the window, install the jamb flashing, install the head flashing, fold the WRB flap down and tape the diagonals; then inspect before cladding covers the work. The pan flashing box is outlined in red where AFS's metal sill pan is used.Read the maker'sinstructions firstCut the WRB, fold jambs in,fold the head flap up1Install the pan flashing:cover rough sill, wall face2Set the window to themaker's instructions3Jamb flashing over thewindow flange and the pan4Head flashing (TN05 step 5)over and beyond the jamb5Fold the WRB flap down;tape the diagonals6Inspect before thecladding covers it

A top-to-bottom flow of eight boxes: read the maker's instructions, the TechNote's six numbered steps from preparing the WRB to folding the flap down, then inspect.

1
Prepare the WRB at the opening
2
Install the pan flashing
3
Set the window to the maker's instructions
4
Install the jamb flashing
5
Install the head flashing (TN05 step 5): over and beyond the jamb flashing, and over the drip cap if installed
6
Fold the WRB flap down and tape the diagonal seams
Steps 1 to 6 are the 2015 builder TechNote's own numbered steps (flanged window installed after house wrap). TN05 step 5 says the head flashing goes over and beyond the jamb flashing, and over the drip cap if installed; it says self-adhesive flashing is common for jamb and head flashing. The pan flashing is outlined in red where AFS's metal sill pan is used. Rules from DuPont, Pella or BSC are on the following slides, not in this order. Always read the product maker's instructions first.

Glossary

House wrap flap
The flap of water-resistive barrier cut at the head of an opening, folded up while the pan, window and flashing go in, then folded down at the end of the TechNote's sequence.
Nail fin (mounting flange)
The flange around a flanged window that is fastened to the wall; makers say not to tape or seal the bottom one so the sill can drain.
Dog ear
A flat folded corner in a sheet metal pan where the end dam meets the back dam, used instead of cutting the corner and sealing the seam.
Splice sleeve
A joining piece under the joint between two lengths of storefront sill flashing; the maker calls for a splice joint between members and sealant over it.
Developed length
The flat length of a formed piece before folding; in AFS's method a sill pan equals the opening width plus extensions plus the two end dam upturns.