Eight defects to look for
Each of these is tied to a published rule on the slides that follow.
- No end dam where the flashing stops
- A dam that stops inside the lintel end
- Flashing stopped behind the face
- Short or unsealed laps
- Punctures at anchors and bolts
- Weeps a course above the flashing
- Weeps clogged, or tube weeps
- Galvanized or aluminum in the mortar
Four rows, correct on the left with a green check and incorrect on the right with an amber border and cross. 1: an end dam turned up on a head flashing, against a flashing cut square with water running off its end. 2: dams beyond the ends of a lintel, against dams stopping inside the lintel ends. 3: flashing past the face with a drip, against flashing stopped behind the face with water wicking down the brick. 4: a weep in the first course immediately above the flashing, against a weep one course higher with water ponding on the flashing.
- 1
- An end dam turned up where the flashing stops, against no dam
- 2
- Dams at or beyond the lintel ends, against dams inside them
- 3
- Flashing to and past the face with a drip, against flashing stopped behind the face
- 4
- Weeps immediately above the flashing, against weeps a course higher
Sources
- Technical Notes on Brick Construction 7: Water Penetration Resistance - Design and Detailing (2017) - Brick Industry Association (Brick Institute of America)
- Technical Notes on Brick Construction 7B: Water Penetration Resistance - Construction and Workmanship (2017) - Brick Industry Association (Brick Institute of America)
- Technical Notes on Brick Construction 7A: Water Penetration Resistance - Materials (2017) - Brick Industry Association (Brick Institute of America)
- Flashing Installation Checklist, Rev. November 2022 (written for flexible membrane flashing) - International Masonry Institute