The method, step by step
Every coping goes on in the same order, set by the guide for the system delivered. The flow chart is the method; each step below is sourced to the maker or standard that prints it.
Where a step fails, stop and ask before the cover goes on.
A vertical flow chart of ten steps with two decision points: read the documents, check the wall, measure; if the wall is outside the tested width in the guide or the limits on the approved shop drawing, stop and ask; order with the maker allowance; membrane and isolation; lay out cleats and joints; corners first; straight lengths with each joint made as the guide shows; end caps restrained; if any stage has not been checked and passed, fix it first; then inspect, photograph and record. A note says the film comes off when the guide says.
- 1
- Read the spec, approved shop drawing and maker guide
- 2
- Check the wall and nailer as built
- 3
- Measure the wall at several points
- 4
- Order or fabricate with the maker's allowance
- 5
- Membrane over the top; isolate metal from treated wood
- 6
- Lay out cleats under every coping end; no short pieces together
- 7
- Corner cleats and miters first
- 8
- Straight lengths, each joint as the guide shows: splice plate and sealant where it has one, a lap over a notch on Econo Coping
- 9
- End caps, end terms and butt walls, restrained
- 10
- Inspect, photograph and record. The protective film comes off when the guide says: Englert before installation, Polyglass immediately
Sources
- Drexel Metals ES-1 installation guides - Drexel Metals
- Installation Guide for Snap Coping-Max/Max-C - Drexel Metals
- Polyforza Coping, Flat or Tapered Version, 3'-0" O.C. - Installation Instructions (DWG 45111-39196 A, 08/01/22) - Polyglass U.S.A.
- R-Mer Force Coping, Premium Metal Edge System: Installation Guidelines (0825) - The Garland Company, Inc.