Before the first nail
Before the first nail, have the project specification, the approved shop drawings, the Drexel guide for the system delivered and the membrane maker's edge detail on the roof.
Where they disagree, stop and ask the designer and AFS before cutting anything.
Choose and set up the fall protection that 1926.501(b)(10) allows before anyone works at the edge.
Sources
- Drexel Metals ES-1 installation guides - Drexel Metals
- 29 CFR 1926.501 - Duty to have fall protection (CFR 2024 annual edition, title 29 volume 8) - U.S. Government Publishing Office (govinfo), OSHA regulation