The path from leak call to closed-out repair
A suggested order built from the sources, not set by UFC or NRCA: safety plan, warranty check, history, interior map, exterior survey, non-destructive method if needed, designed water test if needed, repair to the documented cause, verification, record.
UFC is for U.S. military projects; here it is a model, not a general rule.
Diagram: the flow chart shows the same path with its decision points.
Flow chart of ten steps from the safety plan and warranty check through survey, a non-destructive check when needed, an optional water test, repair to the cause, repeating the same check and recording the result.
Sources
- UFC 3-110-03 Roofing (1 May 2012, Change 5, 12 June 2020): maintenance inspection, leak location and warranty sections - U.S. Department of Defense (USACE, NAVFAC, AFCEC), published by WBDG
- Tech Today: roof inspection and maintenance (Mark S. Graham, Professional Roofing) - National Roofing Contractors Association