Architectural Flashing Supply
Start a Quote
Procurement, supplier qualification and logistics · Lesson 1 of 4

Procurement, supplier qualification and logistics: principles and terminology

The chain that moves metal from a mill to a jobsite, what qualifying a supplier means, the paperwork at each station, who bears the loss in transit, and the storage and handling safety rules.

You will be able to: Describe the chain from mill to jobsite, read the words on the paperwork, say who bears the loss in transit, and state the storage and handling safety boundaries.

9 min · 8 slides · 7 questions

All lessons in this module
Slide 1 of 8

From mill to jobsite

Sheet metal reaches a job through a chain: a mill or service center supplies the sheet, a fabricator forms it, a carrier moves it, and a receiver checks it.

Each station keeps a record, and the record is what settles an argument later. The figure shows what each station holds.

The supply chain and the paperwork at each stationFour stations top to bottom. A, mill or service center, with the mill certificate. B, the AFS shop, with the order wording. C, the carrier, with the bill of lading listing consignor, consignee, origin, destination, packages and description of freight. D, the receiver, with the delivery receipt. Between B and C an amber note says that with no destination named risk of loss passes to the buyer at the carrier and with one named at that destination.From mill to jobsiteAMill or service centerMill certificateThe material record. Compare it with theorder wording.BAFS shop (fabricator)Order wordingMaterial, thickness, finish, and whetherchemical treatment is or is notrequired.Risk of loss: with no destinationnamed, it passes to the buyer at thecarrier. With one named, at thatdestination.CCarrierBill of ladingConsignor and consignee, origin anddestination, packages, description offreight.DReceiverDelivery receiptJobsite or will-call counter. Count,condition and notes, written before thedriver leaves.UCC 2-509 uniform text; your state governs.

Four stations top to bottom: a mill or service center with its mill certificate, the AFS shop with the order wording, a carrier with the bill of lading and a receiver with the delivery receipt, and an amber note on risk of loss between the shop and the carrier.

A
Mill or service center, with the mill certificate
B
AFS shop, the fabricator, with the order wording
C
Carrier, with the bill of lading
D
Receiver at a jobsite or will-call counter, with the delivery receipt
Each station holds a record. Risk of loss depends on whether a destination is named (UCC 2-509 uniform text; your state’s version governs). Bill of lading contents: 49 CFR 373.101. The AFS shop is drawn in red because it is AFS.

Sources

Glossary

Supplier qualification
Checking, before a first order and again on a schedule, that a source can meet your requirements. The federal responsibility standards are a public example of the headings to ask about.
Bill of lading
The carrier’s record of a shipment. It names the consignor and consignee, the origin and destination, the number of packages and a description of the freight.
Consignor and consignee
The consignor is the party that ships the freight and the consignee is the party it is shipped to. Both are named on the bill of lading.
Risk of loss
Which party bears the loss if goods are damaged in transit. Under the uniform text it depends on whether the contract names a destination, and the contract can change it.
Working load limit
The most load a cargo securement component may carry in normal service, usually set by its maker. The federal securement rules count tiedowns by this rating.