Material takeoffs and quantity reconciliation · Lesson 1 of 4

Material takeoffs and quantity reconciliation: principles and terminology

What a takeoff is and is not, the vocabulary of runs, pieces, girth, strips and sheets, the five quantities that are never mixed, how a schedule is read, and who uses the numbers.

You will be able to: Define takeoff, run, piece, girth, strip, sheet, net and gross; say what a takeoff contains and does not contain; and trace one number from a drawing schedule to the shop.

10 min · 10 slides · 7 questions

All lessons in this module
Slide 1 of 10

What a takeoff is

A takeoff measures a drawing set and its schedule and counts the material and accessories the work needs.

McCormick Systems, an estimating-software maker, describes it as "extracting measurements and calculating material quantities from blueprints".

AFS's own takeoff tool reports quantities and weights, never prices, and a dollar figure appears only on a formal AFS quote.

Glossary

Takeoff
The step that measures a drawing set and its schedule and counts the material and accessories the work needs. At AFS it reports quantities and weights, never prices.
Run
The total length of one tagged flashing item on the building, in linear feet. A run is cut into pieces.
Piece
One fabricated length cut from a run. The takeoff states how many pieces a run becomes and which piece length it used.
Girth
The flat width of a profile before it is bent, found by adding its leg lengths. A strip of that width is cut from the 48 in sheet.
Strip
One piece's flat blank, cut along the 10 ft length of a sheet, so its width comes out of the 48 in dimension.
Net and gross
Net is the material in the finished pieces; gross is the sheets or coil ordered to make them. The difference is offcut plus any stated allowance.