Material takeoffs and quantity reconciliation · Lesson 4 of 4

Material takeoffs and quantity reconciliation: defects, verification and case study

Nine takeoff defects with their checks and corrections, among them a wall height read as a flashing leg, a double count, a wrong unit scale, a count rounded down, a sheet count from area, and a girth with the wrong hem, plus what a reviewer should be able to rebuild.

You will be able to: Diagnose a takeoff defect from its symptom, name its cause, choose the check that proves it and the correction, and document evidence a reviewer can rebuild.

11 min · 12 slides · 6 questions

All lessons in this module
Slide 1 of 12

Glossary

Attribution
Deciding which drawn element a dimension measures. In AFS's drawing takeoff a dimension on a building element, or one that cannot be attributed to the flashing, is never a flashing leg.
Coil piece
A piece longer than 10 ft. AFS's Material Takeoff tool lists it apart from the sheet strips and gives an error for one over 126 in.
Confidence
The high, medium or low tag AFS's takeoff puts on each item it reads. Anything not high is flagged for a person to check.
Hem allowance
The extra flat width a hem uses. FlashDraft's figure is approximate: an open 0.5 in hem with a 1/8 in gap adds 1.125 in and a smashed 0.5 in hem adds 1 in.