Field quality plans and inspection records: methods and worked application

A step-by-step method for a field quality plan, from defining the feature through the preparatory, initial and follow-up phases and the triggers that repeat them, with worked examples for piece counts and a thickness check, and a field check card.

You will be able to: Write a one-page field quality plan for a run of flashing: define the feature, list the governing documents, run the three phases of control, say when to repeat them, and record piece counts and thickness checks with their units and assumptions.

12 min · 12 slides · 9 questions

All lessons in this module
Slide 1 of 12
Worked example

Step 1: define the feature

Name the unit the plan controls. Illustration, not a real project: the east parapet coping run, 400 in long, in 24 ga galvanized steel.

UFGS 01 45 00 describes a feature of work as separate and distinct, with its own crew and control requirements. In this illustration the coping run could be treated as one feature; the specification ties each feature to an item in the project schedule.

Sources

Glossary

Preparatory phase
The meeting held before work starts on a feature, after approvals and with materials on site, to review documents, measurements, materials and safety (UFGS 01 45 00).
Initial phase
The check made when crews are ready to start: the first segment is observed, compared with samples and located for later comparison (UFGS 01 45 00).
Follow-up phase
Daily or more frequent checks of the work, recorded in the daily report, until the feature is complete (UFGS 01 45 00).
Splice lap
The overlap where one piece of a run joins the next; with a lap every piece after the first gives up the lap to the joint in AFS's piece-count rule.