Slide 1 of 11

Why the perimeter fails first

IIBEC reports that nearly 60 percent of damaged roofs in post-hurricane studies were caused by failure at the perimeter.

Poor workmanship and lighter-gauge value engineering were the main causes reported.

FEMA also says low-slope membrane roofs often fail at the edges.

Glossary

Assembly-as-tested rating
An ES-1 rating applies only to the assembly as tested: its materials, thicknesses, fasteners, fastener locations and installation method. Changing any of them voids the match.
Sustained pressure
The term Drexel Metals uses for the pressure an ES-1 test assembly sustained. It is the maker's tested value, not a design demand, and the Design Engineer must apply the factor of safety.
Verification chain
The five checks from specification to roof: drawings and spec, submittal, shop, installation, and inspection after a storm, each asking whether the work matches what was tested and the design pressure.
Blanket certification