Production throughput and material yield
The words for how fast work leaves a shop and how much of each sheet ends up in finished pieces, how AFS's sheet and limits decide strips per sheet, a worked takeoff and throughput method, and how to find, fix and record yield and lead-time defects.
4 lessons · about 40 min · 8 diagrams · 5 videos
Version 1.0.0
Builds on these modules
Related Academy lessons
Lessons
0 of 4 complete
Lesson 1 · 12 min · 12 slides · 9 questions
Production throughput and material yield: principles and terminology
The words a shop uses for how fast work leaves it and how much of each sheet ends up in finished pieces, and the machine-guarding and lockout rules that no schedule overrides.
You will be able to: Define throughput, cycle time, lead time, takt, work in process, the constraint, utilization, drop and first-pass yield, state Little's Law with units, and state the safety rules that speed never overrides.
Not startedStart →Lesson 2 · 9 min · 8 slides · 7 questions
Production throughput and material yield: materials, standards and design constraints
How AFS's 10 ft x 4 ft sheet, the blank width and the length limits decide how many strips a sheet gives, why a width just past a breakpoint wastes a whole strip, and what the sheet weighs.
You will be able to: Work out strips per sheet from a blank width, spot a width just past a breakpoint, apply AFS's girth and length limits and stock convention, and say what the sheet standards do and do not cover.
Not startedStart →Lesson 3 · 10 min · 11 slides · 7 questions
Production throughput and material yield: methods and worked application
AFS's takeoff method step by step, first fit decreasing in plain words, a worked job with and without a cut allowance, and worked throughput examples for lead time and the constraint.
You will be able to: Run AFS's takeoff method by hand on a small job, show the effect of a cut allowance, estimate lead time with Little's Law and find the constraint, recording every assumption and unit.
Not startedStart →Lesson 4 · 9 min · 11 slides · 6 questions
Production throughput and material yield: defects, verification and case study
The common ways a shop loses metal or time, how to check a plan against what the shop really pulled, a worked case on a wide profile, and the evidence packet a reviewer needs.
You will be able to: Diagnose a yield or throughput defect from evidence, compare planned with actual sheets, utilization and first-pass yield, explain corrective options and who decides them, and assemble the evidence for review.
Not startedStart →
Practical task
Plan and verify a small order of 24 ga galvanized flashing: three lines you choose from FlashDraft profiles without hems, at least one shorter than 120 in and none longer than 126 in. Work out strips and sheets, check every width for the width cliff, estimate lead time from given shop numbers, and write up one defect.
Hand in
- The line list: profile, blank width, piece length and quantity, each with units and where the width came from
- Strips per 48 in sheet for each width, with the nearest breakpoint (48 / k) and the drop beside the strips
- A takeoff, by hand or with the Design Center material takeoff, with the cut allowance stated, the strip and sheet counts and the utilization
- A marked-up layout sketch of the strips on each sheet, drops shown
- A lead-time estimate by Little's Law from a stated work in process and finishing rate, with units
- One defect analysis (for example short pieces one per strip, or a width just past a breakpoint): the evidence, the fix, who decides it, and what you will check after the run
Rubric
| Criterion | Meets the standard when |
|---|---|
| Strips per sheet | Each width gives floor(48 / width) strips, the drop is right, and any width just past a breakpoint is flagged. |
| Takeoff | Pieces are pooled by material, thickness and width; the strip and sheet counts and the utilization match the method, and the cut allowance is stated. |
| Limits | No blank is wider than 48 in, no piece is longer than 126 in, and pieces over 10 ft are listed as coil pieces. |
| Throughput | The lead time is work in process divided by throughput, with units, and the constraint is named from the rates given. |
| Evidence | The defect write-up states what was seen, the fix and its owner, and the planned-versus-actual checks; no prices appear anywhere. |