Fascia LT installation sequence

ANSI/SPRI/FM 4435/ES-1 edge system: 22 Gauge Cont Cleat, Snap-On Cover, 10' Lengths. 3", 4.5", 6", 8" faces.

Drexel guide (PDF)

This sequence follows Drexel Metals' published installation guide for the system. The project's specifications, the approved shop drawings and the roofing membrane manufacturer's requirements govern; where they differ, follow them and ask AFS. Source: Drexel Metals, “Installation Guide for Fascia Cover LT”.

Step 1 of 4

Installing 22GA Galvanized Cleat

  1. Apply water cut-off mastic and place the face of the cleat squarely on the edge of the roof membrane, over the wood nailing plate.
  2. Press it firmly into position and screw through the pre-punched face holes.
  3. At a miter, miter-cut the cleat into the corner as required to keep a continuous cleat line, then fasten at a minimum 6" in each direction from the corner, or closer at special conditions.
  4. Butt the cleat ends and apply tube sealant over the butted ends.

As printed in the Drexel guide

“screw through the pre-punched face holes with #10-13x1" S.S. Panhead Woodscrews provided.”

Common mistakes this step guards against

  • Do not leave butted cleat ends unsealed - apply tube sealant over them.
  • Do not break the cleat line at a corner - miter-cut it so the line stays continuous.
Loading 3D view…
This step does not install the cover. Shown: the FlashDraft “Fascia Cover” section, the cover only - the cleat, splice plates and fasteners are in the parts list.

Parts, lettered as in the guide

  • AFascia Cover LT Flashing 10'-0" Std. Lengths
  • BFascia Cover LT Splice Plate 6" Lengths
  • C22GA Continuous LT Cleat 10'-0" Lengths
  • DFascia Cover LT Miter (Outside Corner Shown)
  • E#10-13x1" S.S. Panhead Woodscrew at 12" o.c. (6" from ends) (Included & Required)
  • FApproved Roofing Membrane (By Installer)
  • -Water Cut Off Mastic Shown under the cleat face
  • -Tube Sealant Shown at splice plates and butted cleat ends

Field checklist

Fascia LT - from Drexel's guide. Tick each item as it is done; print this page for the crew.

Common mistakes

Each line is the reverse of an instruction the Drexel guide states.

  • Do not leave butted cleat ends unsealed - apply tube sealant over them. (step 1)
  • Do not break the cleat line at a corner - miter-cut it so the line stays continuous. (step 1)
  • Do not butt lengths tight - leave the 1/8" gap for thermal expansion. (step 4)
  • Do not leave a joint without a splice plate. (step 4)
  • Do not cut lengths that leave short sections next to each other. (step 4)

Notes printed on the guide

  1. Isolate all metal parts from ACQ-treated wood, or any other galvanically incompatible material, with an appropriate membrane.
  2. Appliance attachments - lightning rods, signs, antennae - that penetrate the water seal, set up a galvanic reaction or otherwise compromise the roof edge system are to be eliminated or isolated, per section 8.0 of ANSI/SPRI ES-1. Isolate appliances from the edge system or do not attach them to it; the lightning protection manufacturer gives the attachment instructions.

Printed on the section detail

  • Face height 8" max. / 3" min. (Fascia Cover LT print approval DM-15488)
  • #10-13x1" S.S. Panhead Woodscrew 12" on center through pre-punched cleat hole and membrane
  • Water cut-off mastic under the cleat face

Drexel published ratings

Sustained pressure as Drexel publishes it (Drexel Metals DM-19063 "ES-1_GT-1 Certification Program Product Line Card" 12.09.25). Design Engineer must apply the Factor of Safety.

CoverFace up toWall up toCleatSustained pressure
24 gauge8"-22 ga-210 psf
.040 AL6"-22 ga-180 psf