Base flashing, counterflashing and reglets: methods and worked application

The installer's sequence from layout to fill: marking and cutting the reglet, the deck-versus-roof-surface datum trap, base flashing and termination bar, manufactured reglets, setting, lapping and cornering the counterflashing, and five worked calculations.

You will be able to: Follow a documented installation sequence for a regleted counterflashing over a membrane base flashing, check reglet height, lap and clearance from the finished roof surface, and work out pieces, wedges, termination-bar fasteners and dust-collector airflow with every assumption recorded.

11 min · 12 slides · 6 questions

All lessons in this module
Slide 1 of 12

The installation sequence

Read the governing documents; lay out the reglet; set up fall protection and silica controls; cut or set the reglet; clean; install the base flashing and termination; set the counterflashing the same day; wedge, lap and corner; fill; inspect; report measured sizes back to the fabricator.

The installer's sequence at a roof-to-wall jointEleven numbered steps from top to bottom: read the governing documents, lay out the reglet measuring from the roof surface, set up fall protection and silica controls, cut or set the reglet, clean with wet methods or a HEPA vacuum, install base flashing and termination, set counterflashing the same day, wedge, lap and corner, fill the reglet, inspect and record, and report real sizes to the fabricator. On a reroof, a decision after step 1 asks whether existing metal is sound: if rusted or damaged it is replaced.One run, start to finish1Read the documents2Lay out from roof surface3Fall and silica set-up4Cut or set the reglet5Clean: wet or HEPA6Base flashing + termination7Counterflashing same day8Wedge, lap, corner9Fill the reglet10Inspect and record11Report sizes to fabricatorReroof:reuse?Rusted ordamaged:replace(IBC-based1512.4).Sound: perthe roofmaker'sdetail.Step 3: 29 CFR 1926.501 and 1926.1153.Step 5: 1926.1153(f). Step 7: if thecounterflashing waits, seal the base top.

Flow of eleven numbered steps from reading the governing documents, through layout, safety set-up, cutting, cleaning, base flashing and termination, same-day counterflashing, wedging and lapping, filling and inspection, to reporting measured sizes back to the fabricator, with a decision on whether existing counterflashing can be reused.

1
Read the governing documents: code, specification, roof and reglet manufacturer
2
Lay out the reglet with the designer; measure from the roof surface
3
Safety set-up: fall protection and Table 1 silica controls
4
Cut the reglet (ends raked out to full depth, joint width kept, level or outward) or set a manufactured reglet
5
Clean with wet methods or HEPA vacuum, no dry sweeping or compressed air
6
Install base flashing and termination to the roof maker's instructions
7
Set counterflashing the same day, or seal the top of the base flashing
8
Leading piece first; wedges; laps; corners
9
Fill the reglet with mortar or sealant, per specification
10
Inspect and record measured values
11
Report real depths and lengths to the fabricator
One run, start to finish. The reuse decision comes from the metal's condition (IBC-based 1512.4) and the roof manufacturer's detail.

Glossary

Datum
The surface a height is measured from. UFGS 07 60 00 measures reglet height from the roof deck; membrane makers measure base flashing height from the roof surface, so insulation thickness sits between the two.
Spring action
UFGS 07 60 00 term: the counterflashing is installed so it presses back against the base flashing.
Loose-lock
Levine's term for hooking the hemmed bottom edges of two lapped counterflashing pieces loosely together, so the lap stays closed and can still move.
Gusset plate
A small plate of matching metal soldered into an inside corner of a counterflashing to make the corner watertight (Levine).
Leading counterflashing
The first piece set in a run; Levine fills the part of the reglet the next piece will cover before setting that next piece.