A path from idea to tested detail
This seven-step path is a course teaching sequence built from ES-1's requirements and NASA's verification ideas. It is not a published SPRI procedure.
NASA says validation can be performed in each development phase using phase products such as models, not only at delivery.
Seven boxes lettered A to G, top to bottom, from the requirement to fabricating only as tested, with a dashed arrow from the laboratory test back to the drafted detail if it fails.
- A
- Requirement from the code and wind loads (ES-1 commentary: the tested strength must meet or exceed the required pressures)
- B
- Choose the test method: RE-1, RE-2 or RE-3 (ES-1 sections 2 and 3)
- C
- Draft the detail and its installation instruction (ES-1 section 5)
- D
- Build full-size production specimens, at least 96 in. long (ES-1 RE-2 and RE-3 specimens)
- E
- Independent laboratory tests the specimens (ES-1 commentary, SPRI seminar)
- F
- Report, labelling and packaging documents (ES-1 section 4)
- G
- Fabricate only as tested and control changes (SPRI ES-1 FAQ, five conditions)