Four faults to catch
Most corner faults are set up before anyone climbs the roof: in the takeoff, the cut list and the order. The drawing pairs a right and a wrong way for four of them, and names whose rule each is.
Four pairs, correct on the left and wrong on the right: a cleat joined through the corner versus a cleat broken at the corner; a full piece beside the miter versus a sliver beside it; a miter end with splice plate and sealant versus a bare butt joint; a sloped run ordered at its true length of 17.889 ft versus at its 16 ft plan length, 22-11/16 in short.
- 1
- Cleat at the corner: joined as the system's guide shows (a continuous cleat line on Drexel drip edge, fascia and gravel stop), not broken off
- 2
- Last piece: 12 in or more, never a sliver beside the miter
- 3
- Miter end: splice plate and sealant bead, not a bare butt joint
- 4
- Sloped run: ordered at 17.889 ft true length, not 16 ft plan length
Sources
- Design Center roof edge, coping and fascia quantities (corner types, true length, pieces, closer check) - Architectural Flashing Supply
- Drexel Metals ES-1 installation guides - Drexel Metals
- Installation Guide for Snap Coping-Max/Max-C (2019) - Drexel Metals, Inc.