The anatomy of a good RFI
In the California courts contract, an RFI sets out the single issue, the Specification Section, article, drawing and detail involved, and why a response is required.
It also states the contractor's own interpretation and the reasons for it.
Two forms. The poor one has no number, no reference, several subjects in one RFI, and no proposed fix or date. The good one has a number, one subject, the specification section, sheet and detail cited, the contractor's own reading, a proposed fix and a needed-by date.
- 1
- No number
- 2
- No reference to a sheet, detail or specification section
- 3
- Several subjects in one RFI
- 4
- No reading, no proposed fix and no needed-by date
- A
- A number from one numbering system
- B
- A single subject
- C
- Specification section, sheet and detail cited
- D
- Own reading, a proposed resolution and a needed-by date
Sources
- Attachment F, General Conditions of the Agreement for Construction (Document 00 70 00), San Joaquin juvenile justice center, 2013 - Judicial Council of California (Administrative Office of the Courts)