RFIs, change orders and document control · Lesson 2 of 4

RFIs, change orders and document control: materials, standards and design constraints

The documents that make up a contract, the reply, notice and review clocks in three real contracts, why a missing notice costs money, what an approved submittal does not do, and the physical limits any change still has to meet.

You will be able to: Identify the documents that govern a change (contract conditions, specification, code, standard and shop limits), read the clocks and caps they set, and say which belong to the owner, the code and AFS.

14 min · 12 slides · 12 questions

All lessons in this module
Slide 1 of 12

The documents that govern a change

At the University of Michigan, the Contract Documents include the Drawings, Specifications, Change Orders and Construction Change Directives.

A Modification there is a written amendment signed by both parties, a Change Order or a Construction Change Directive; Design Professional interpretations are not Modifications.

Sources

Glossary

Contract Documents
The set that makes up the contract. At the University of Michigan it includes the Drawings, Specifications, Change Orders and Construction Change Directives.
Calendar day
Every day counts, including weekends. The California courts contract defines a Day as a calendar day unless it says otherwise; a working day is a different unit.
Equitable adjustment
A fair change in contract price, schedule or both when a change order increases or decreases the cost or time of the work, as federal construction contracts use the term.
Submittal register
The running list of every required submittal with the dates each was received and returned, kept up to date as the work progresses.
Girth
The total flat width of a profile, hems included: the sheet width that must be cut to make it. AFS's design tool counts each hem as an approximate allowance, not an exact bend deduction. AFS can make a girth up to 48 inches.