Plan backward from the install
Plan backward: start from the day the crew needs the material, then subtract each step.
Because AFS books delivery for the next business day after a job is marked finished, work back one business day from the delivery day to find the finish day.
Each step starts when the one before it ends.
Two panels. Wrong, marked with a cross: finished Friday, the crew starts Monday at 7 AM and the delivery is booked in the Monday 8 to 10 window so the crew waits; or delivered in week 1 for an install in week 3 and stored on site. Right, marked with a check: finished Thursday, delivered Friday, install starts Monday.