The method in six steps
Six steps: take quantities from the takeoff; split the work into activities; choose a rate for each; hours = quantity / rate; adjust for conditions; then set crew, duration and a plan to track actual hours.
UFC 3-740-05 says estimating labor productivity has many diverse, unpredictable factors, and no substitution for the knowledge and experience of the cost engineer.
Six boxes in order: quantities from the takeoff in length and counts, activities from the installation sequence, a labeled rate for each activity, hours equal quantity divided by rate, adjust for conditions, and crew, duration and manpower. A loop returns actual hours, checked daily or weekly, to step 3. A bar says hours come first and a wage rate is applied later.
- 1
- Quantities from the takeoff: length and counts
- 2
- Activities from the installation sequence
- 3
- A rate for each activity, labeled: own record, reference or judgment
- 4
- Hours = quantity / rate, with units on every rate
- 5
- Adjust for conditions: a cited multiplier on the affected hours, edge protection, heat
- 6
- Crew, duration and manpower plan, then track actual hours
Sources
- UFC 3-740-05 Construction Cost Estimating (09 December 2022), chapters 5 and 6 - U.S. Army Corps of Engineers, NAVFAC and AFCEC (Unified Facilities Criteria)