Planned versus actual: the Delta
Hanna defines Delta as actual labor hours minus the estimated hours including approved change orders. A positive Delta means actual productivity was worse than estimated.
%Delta is Delta divided by the actual hours.
Causes the study names include an inaccurate estimate, contractor inefficiency, change orders, weather and interruptions.
Sources
- Schedule Compression Effects on Labor Productivity (A.S. Hanna, University of Wisconsin-Madison, 2004; Appendix II multipliers) - New Horizons Foundation (SMACNA resource library)