Architectural Flashing Supply
Start a Quote
Fabrication labor and machine time estimating · Lesson 4 of 4

Fabrication labor and machine time estimating: defects, verification and case study

Six ways an estimate goes wrong, two counting mistakes, setup charged per piece, a wage used as a loaded cost, verification against actuals, a case study of a miscounted 63 ft run, and a twelve-point check before release.

You will be able to: Spot and correct the common defects in a time estimate, separate a wage from a loaded cost, verify an estimate against recorded actuals, and work a miscounted run from discovery to a documented fix.

9 min · 9 slides · 6 questions

All lessons in this module
Slide 1 of 9

Six ways an estimate goes wrong

Six common ways an estimate goes wrong: an operation left out, setup charged on every piece, a piece or girth over the limit assumed makeable, a thickness rule ignored, a wage used as a loaded cost, and a learning curve applied to a one-off.

Each is found by checking the estimate against the drawing and the registers, not by feel.

Glossary

Fixed cost
GAO's idea that some costs do not change with quantity, so unit cost rises when fewer items share them. Setup is the shop version for a batch.
Shop review
AFS's status for a profile the shop must confirm before fabrication; the customer sentence is "AFS confirms this profile before fabrication."
Elapsed time
The calendar span between two events, such as AFS recording when a job first goes in progress and when it is marked complete; it includes waiting.
Time study
A way of collecting data on production by observing work, which BLS lists among the ways industrial engineers collect data on processes.