Construction scheduling and trade interfaces · Lesson 1 of 4

Construction scheduling and trade interfaces: principles and terminology

Critical path, float, hand-offs, procurement as work, weather as a calendar and the fall-protection and site-control rules, all seen from where flashing meets another trade.

You will be able to: Define the schedule terms a flashing crew meets, explain interfaces and hand-offs between trades, and state the safety boundaries for heights and shared sites.

13 min · 12 slides · 10 questions

All lessons in this module
Slide 1 of 12

Flashing is where trades meet

Building Science Corporation says a flashing can protect an interface between two different enclosure elements.

Flashings are needed wherever a drainage plane ends or is interrupted, such as at a roof edge, an opening or a penetration.

Here, an interface is where one trade’s work meets another’s, and a hand-off is when responsibility for a layer passes on (this module’s own terms).

Where layers meet at a roof-to-masonry parapetSection through a masonry parapet and low-slope roof. The roof membrane turns up the wall as base flashing, which ends below a sheet-metal receiver. A counterflashing in red hangs from the receiver over the base flashing. Higher up, a through-wall flashing with a drip sits under weep tubes and the drainage plane laps over it.Roof-to-masonry parapet (section)WallRoof sideABCDEFGRed is AFS-type sheet metal.Not to scale.

Section through a masonry parapet and low-slope roof: the roof membrane turns up the wall as base flashing and ends below a red sheet-metal receiver, with a red counterflashing hanging over the base flashing; higher up a through-wall flashing with a drip sits under a weep tube and the drainage plane laps over it.

A
Roof membrane (installer set by the contract)
B
Base flashing turned up the wall (installer set by the contract)
C
Through-wall flashing with its drip (installer set by the contract)
D
Weep tube (installer set by the contract)
E
Drainage plane, dashed, lapped down over the through-wall flashing (installer set by the contract)
F
Receiver of a two-piece counterflashing, AFS-type metal in red (installer set by the contract)
G
Counterflashing hanging from the receiver over the base flashing, AFS-type metal in red (installer set by the contract)
Schematic, not to scale. Every layer has one owner, and the contract names it; the laps are where two owners meet. Red marks sheet metal of the kind AFS fabricates. The receiver and counterflashing follow the arrangement in the Roofing Magazine photographs; the other layers are general.

Sources

Glossary

Critical path
The longest continuous sequence of activities in a schedule. It sets the earliest completion date, and a delay on it moves the finish by the same amount.
Total float
The amount of time an activity can slip before the project end date is affected. Critical activities have zero total float when the schedule has no date constraints.
Near-critical activity
An activity with little total float, which can quickly become critical if its float is used up by a delay.
Free float
The amount of time an activity can be delayed without affecting any of the activities that follow it.
Constraint
In the Last Planner method, a directive, resource or prerequisite piece of work, not already shown on the plan, that a task needs before it can start and finish.
Interface
In this module, the place where one trade’s work meets another’s, such as roof base flashing meeting a wall. Building Science Corporation describes a flashing as able to protect an interface between two different enclosure elements.
Hand-off
In this module, the moment responsibility for a layer of the building passes from one crew or trade to the next.
Submittal
Information sent to a reviewer to show that the work will comply with the contract documents, such as shop drawings, product data and samples.