The method in seven steps
This module’s own method, drawn from the GAO guide and the Last Planner summary.
- 1 List the interfaces.
- 2 Name an owner for each layer.
- 3 Write each hand-off condition so it is observable.
- 4 Add the paper and shop chain as activities.
- 5 Link, run both passes, read the float.
- 6 Screen each task for constraints.
- 7 Put inspection holds in the weekly plan.