The closeout sequence
UH 01 77 00, one owner's specification, orders closeout this way: paper ten days ahead, written request, inspection, certificate, reinspection, final inspection.
In UH 01 77 00, results of the completed Substantial Completion inspection form the basis of the requirements for final completion.
UH 01 77 00 has the architect prepare a final Certificate for Payment after the final inspection.
Flow chart of seven numbered steps: paper due ten days ahead, written request, architect inspects, a decision on whether items are unfulfilled that loops back to step 2, the written request, certificate and punch list, correct then reinspect, certified list and final request, final inspection.
- 1
- Closeout submittals, training and cleaning done at least 10 days before the request
- 2
- Written request for the Substantial Completion inspection
- 3
- The architect inspects, or says what is unfulfilled
- 4
- Certificate of Substantial Completion with the punch list; warranties start unless the form says otherwise
- 5
- The contractor corrects the items and requests reinspection
- 6
- Architect's certified list, final application for payment, insurance evidence and the written request for final inspection
- 7
- Final inspection, then the final Certificate for Payment