Specification conflicts and design resolution: principles and terminology

What a specification conflict is, where a statement lives in a section, why the contract itself ranks the documents, why a difference is reported and not decided, and where AFS sits in that chain.

You will be able to: Name the six kinds of specification conflict, say who ranks the contract documents and who answers a question about them, tell a conflict from a gap, and state what a fabricator never decides alone.

11 min · 11 slides · 8 questions

All lessons in this module
Slide 1 of 11

Six kinds of conflict

A specification conflict is two statements that cannot both be satisfied, or a needed fact that is missing. Edge metal work shows six kinds:

  • a drawing against a specification
  • one section against another
  • a document against a code or standard edition
  • a document against a manufacturer's instruction
  • one number printed two ways
  • a gap: a needed fact not stated at all

Sources

Glossary

Contract documents
The drawings, specifications and other documents a contract names; the work is held to them. Each contract defines its own list and its own order of precedence.
Specification conflict
Two statements in the documents that cannot both be satisfied, such as a drawing against a specification, one section against another, or a number printed two ways.
Gap
A needed fact that is not stated at all, such as the metal or the finish. AFS tools return "not specified" for it instead of guessing.
Order of precedence
A contract's own rule for which document wins when two differ. FAR 52.236-21 says the specifications govern over the drawings; other contracts say it differently.
Authority having jurisdiction
The body that adopts and enforces the building code for a project and sets local criteria. In the proposed ED-1 revision, local codes and the authority having jurisdiction ultimately dictate edge metal performance requirements.
Variation
A departure from a contract requirement. UFGS 01 33 00 says variations require Contracting Officer approval and must be specifically pointed out.