ANSI/SPRI/FM 4435/ES-1 edge systems: methods and worked application

A seven-step method, a worked wind screening at one corner, three bases that change a verdict, piece-length planning, the install order for drip edge, fascia, gravel stop and coping, nailers and isolation, fall protection and the job packet.

You will be able to: Apply a documented method: find demand, pick a tested assembly, check its configuration, plan piece lengths, install in sequence and record the assumptions.

11 min · 12 slides · 6 questions

All lessons in this module
Slide 1 of 12

The method in seven steps

A working method has seven steps: find the demand, pick the edge type and test method, pick a tested assembly whose size window covers the job, check the build against its record, get the certificate for that assembly, install as tested, and file the record.

If no tested assembly covers the job, ask the engineer of record: a custom shape carries no ES-1 rating.

Choose and document a tested edge: seven stepsSeven numbered steps down the page: find the demand, pick the edge type and test method, pick a tested assembly whose window covers the job, check the build against the record, get the certificate, install as tested, and file the record. A note after the steps: if no assembly covers the job, ask the engineer of record.1Find the demand2Pick edge typeand test method3Pick an assembly whosewindow covers the job4Check the buildagainst its record5Get the certificatefor that assembly6Install as tested7File the recordNo assembly covers the job?Ask the engineer of record.

Seven numbered steps down the page: find the demand, pick the edge type and test method, pick a tested assembly whose window covers the job, check the build against its record, get the certificate for that assembly, install as tested, file the record, with a note to ask the engineer of record if no assembly covers the job.

1
Find the demand from the project's wind data, set by the engineer of record
2
Decide whether the edge is a fascia-type face (RE-2) or a coping (RE-3)
3
Pick a tested assembly whose face and wall window cover the job
4
Check metal, gauge, cleat, fasteners and spacing against the assembly's record
5
Get the ES-1 certificate of compliance for that assembly
6
Install in the maker's order with the maker's fasteners and gaps
7
File the certificate, drawings, wind basis and checklist
A working method for this course, built from SPRI, IIBEC and NRCA guidance.

Sources

Glossary

Strength level
The wind pressure from the ASCE 7 method before any allowable-stress factor or safety factor is applied, as AFS's Design Center screening calculates it.
Splice plate
A 6 in plate placed under the ends of adjoining edge-metal pieces at a joint; the Drexel Drip Edge and Fascia LT guides and the Petersen Aluminum Gravel Stop guide call for one at every joint, while Drexel's Econo Coping LT guide lists none and overlaps the coping pieces.
Kickout
The formed lip on a cleat that the drip of the cover hooks onto during installation in Drexel's drip edge and coping guides.
Mean roof height
The height h used in the wind-pressure calculation; AFS's Design Center screening covers buildings up to 60 ft.