The specifier's sequence
Two steps serve a specifier: the engineer of record works out the design pressures for each edge condition, then you choose a tested edge that meets or exceeds them.
ES-1's commentary says copings must be tested to RE-3 and provide a strength that meets or exceeds the horizontal and vertical pressures required.
A column of nine steps: codes and ASCE 7 edition; wind speed for the Risk Category; exposure, height, Kzt and Ke; velocity pressure; roof and wall zones with GCp; pressure basis and factor; design pressure per edge; tested edge RE-2 or RE-3; install as tested and keep the papers. A red bracket marks steps 3 to 5 as covered by AFS screening; a navy bracket marks steps 6 and 7 as the engineer of record.
- 1
- Confirm the code and the ASCE 7 edition the jurisdiction adopted
- 2
- Read the basic wind speed for the Risk Category
- 3
- Set exposure, mean roof height, Kzt, Ke and enclosure
- 4
- Work out the velocity pressure qh
- 5
- Apply roof and wall zones and their coefficients
- 6
- Choose the pressure basis and the factor of safety
- 7
- State the design pressures for each edge condition
- 8
- Choose an edge tested by RE-2 or RE-3 to meet them
- 9
- Install exactly as tested and keep the documentation